Emergency lighting is one of those systems people only notice when it fails, which is exactly why the testing routine matters.
In apartment blocks, communal escape routes rely on shared lighting arrangements being there when normal power fails. That is why emergency lighting should not just be installed and forgotten. For practical fire-safety management, weekly or routine fire-safety checks, monthly emergency-lighting checks and formal annual testing all matter. Greater Manchester Fire and Rescue Service says emergency lighting should be tested once each month, and the Fire Protection Association says the usual BS 5266 approach is a monthly functional test plus an annual full-duration test.
What block managers need to know
For communal emergency lighting, the usual practical schedule is:
- routine visual awareness as part of managing the building
- monthly functional checks
- annual full-duration testing
- clear records of defects and follow-up works
This is the pattern most people are really asking about when they search for testing frequency. It is not enough to know the lights are installed. You need to know the checks are actually being done and recorded.
Why apartment blocks need a proper schedule
Communal areas in blocks are not just decorative shared spaces. They are part of the escape route.
That means stairwells, corridors, landings and entrances often rely on emergency lighting as part of the building’s life-safety setup. The GOV.UK and Home Office fire-safety guidance for blocks of flats makes clear that the common parts of multi-occupied residential buildings sit within the building’s fire-safety duties.
Monthly checks
Monthly checks are usually short functional tests.
The practical aim is to confirm that the fittings operate when normal power is interrupted and that obvious defects are picked up early. GMFRS says emergency lighting should be tested once each month as part of maintenance and records. The FPA gives the same practical direction, describing monthly “flick tests” alongside the annual full-duration test.
Annual full-duration test
The annual test is the one people most often remember, but it is not the only one.
The full-duration test is there to confirm the system can operate for its rated duration, not just switch on briefly. The FPA describes this as the annual full-duration test under BS 5266, and the recent NICEIC summary of BS 5266-1 confirms that the 2025 edition is now in force.
Records matter as much as the test
A building is in a much stronger position if it can show:
- when the monthly checks were done
- when the annual test was done
- what defects were found
- what remedial work followed
- whether the issue was actually closed out
GMFRS explicitly asks dutyholders what maintenance they need to do and what records they should keep, which is the right practical mindset here.